Lectures:
1. Introduction, structure, themes and objectives of the course
2. The types of concretes
3. – 5. Implementation of special concrete structures HSC, UVPB,
6. Implementation of structures SCC
7. Testing of concrete, technological procedure of wire reinforced concretes
8. Using the structural system white tub with safety system
9. Implementation of working and expansion joints with a focus on specific design requirements
10. – 11. Stabilization of objects with progressive methods e. g. Helifix
12. – 13. Options of strengthening of existing structures e.g. FRP
14. Conclusion
Practice:
1. Introduction, structure and objectives of the course
2. – 3. Assessment of the proposal for building foundations
4. Control entrance tests Implementation of the buildings I – collective repair of the test
5. – 7. Foundation of a building on large-diameter piles
8. Control entrance tests Implementation of the buildings II – collective repair of the test
9. – 11. A proposal of implementation of masonry redevelopment (technological procedure)
12.- 13. Control course credit test
14. Time reserve – programs completion and tests repairs
1. Introduction, structure, themes and objectives of the course
2. The types of concretes
3. – 5. Implementation of special concrete structures HSC, UVPB,
6. Implementation of structures SCC
7. Testing of concrete, technological procedure of wire reinforced concretes
8. Using the structural system white tub with safety system
9. Implementation of working and expansion joints with a focus on specific design requirements
10. – 11. Stabilization of objects with progressive methods e. g. Helifix
12. – 13. Options of strengthening of existing structures e.g. FRP
14. Conclusion
Practice:
1. Introduction, structure and objectives of the course
2. – 3. Assessment of the proposal for building foundations
4. Control entrance tests Implementation of the buildings I – collective repair of the test
5. – 7. Foundation of a building on large-diameter piles
8. Control entrance tests Implementation of the buildings II – collective repair of the test
9. – 11. A proposal of implementation of masonry redevelopment (technological procedure)
12.- 13. Control course credit test
14. Time reserve – programs completion and tests repairs